Replacement Air Conditioning installation at Jaltek

An improved working environment for a leader in electronic design

Jaltek, a leader in electronic design and manufacturing located in Luton, required an upgrade to their existing air conditioning systems. Their existing system had become inefficient and unsuitable for the thermal loads of their production area and additional facilities.

Jaltek introduction image

The project background and key requirements

The project aimed to enhance the indoor climate for both staff and production processes while ensuring compliance with current environmental regulations, including F-Gas and WEEE.

Project objectives

1. Removal of the old system

Remove and dispose of the existing air conditioning systems in compliance with F-Gas and WEEE legislation.

2. Install the replacement system

Install new, energy-efficient air conditioning systems in designated areas.

3. Improve the working environment

Improve comfort levels for employees and optimise conditions for production.

Scope of work

The project involved the installation of the following air conditioning systems:

1. Production Area: 6 Ceiling-Suspended Systems
  • Designed to effectively distribute air across large spaces
  • High-efficiency units to ensure energy savings
2. Staff Canteen: 1 Ceiling Cassette System
  • Provides uniform cooling and low noise levels
  • Aesthetically pleasing design suitable for communal dining areas
3. Reception Area: 1 Wall-Mounted System
  • Efficient temperature control for guest-facing areas
  • Compact design to blend with the reception decor

Installation process

Site Assessment
  • Tick icon
    Conducted a detailed analysis of the existing air conditioning systems and the required cooling loads for the various areas of the facility.
  • Tick icon
    Engaged with stakeholders to confirm specific needs and preferences.
Removing existing systems
  • Tick icon
    Safely dismantled and removed existing air conditioning units and associated equipment.
  • Tick icon
    Ensured proper disposal of materials in accordance with the F-Gas regulations to minimize environmental impact.
Installation of New Systems
  • Tick icon
    Performed electrical and HVAC system updates as necessary to accommodate new equipment.
  • Tick icon
    Installed ceiling suspended systems in the production area, ensuring optimal air distribution and efficiency.
  • Tick icon
    Installed the ceiling cassette in the canteen and the wall-mounted system in the reception area with precise location planning for comfort and aesthetics.
Testing and Commissioning
  • Tick icon
    Conducted rigorous testing of all installed units to ensure optimal performance and compliance with manufacturer specifications.
  • Tick icon
    Provided operational training to staff on the new systems.
Final Inspection and Handover
  • Tick icon
    Completed a final walk-through with Jaltek to ensure satisfaction and address any remaining questions.

Successful outcomes for Jaltek

  • Tick icon
    Enhanced climate control
    Enhanced indoor climate control in the production area, leading to improved worker comfort and potentially increased productivity.
  • Tick icon
    Improved comfort for staff and visitors
    Improved air quality and consistency in temperature across the staff canteen and reception, positively impacting employee morale and visitor experience.
  • Tick icon
    Legislative compliance
    Achievement of compliance with current environmental legislation, contributing to Jaltek’s sustainability goals.
Affordable Finance

Project conclusion

Energy-efficient Solutions

The successful replacement of the air conditioning systems at Jaltek has resulted in energy-efficient solutions that cater to the current and future needs of the facility. The project not only met the objectives outlined but also positioned Jaltek as a responsible company committed to adhering to current environmental standards.

Future Maintenance
  • Scheduled regular inspections and maintenance to ensure continuous optimal performance of the new systems.
  • Keep abreast of new regulations and technologies to further improve energy efficiency and sustainability.

We commissioned Spheretech to redesign and install a new air conditioning system for our electronics manufacturing facility, and they exceeded expectations at every stage. Their understanding of the technical requirements, commitment to energy efficiency, and seamless project execution ensured minimal disruption to our operations while delivering a solution perfectly tailored to our environment.

Paul Livingstone, Facilities Manager, Jaltek

What our customers say...

 Google rating

Mowbray Workspace have worked with Spheretech for many years. They are attentive and fit in with our Turnkey projects always as required. Their expertise in providing systems to comply with Building Regulations are second to none and have helped us win several projects.

Mowbray Workspace

Mowbray Workspace Solutions

CALL 0808 196 5510

for more information or contact us online

Scroll to top